|
Standards for Actual Output
|
|
| |
Standards for actual output can be seggregated as
Standard Time for Actual Output [ST for AO]
The labour/labor time that should have been used for the actual output, had the labour/labor time been utilised as per the standard.
-
Standard Cost for Actual Output [SC for AO]
The labour/labor cost that would have been incurred for the actual output, had the labour/labor been used (time) and employed (wage rate) at the rates as per the standard.
|
Budgeted/Standard [Output : 80 units] |
Actual [Output : 80 units] |
|
Time (hrs) |
Rate (Rs/hr)
| Cost (Rs) |
Time (hrs) |
Rate (Rs/hr) |
Cost (Rs) |
| Operators |
160 |
12 |
1,920 |
168 |
12.50 |
2,100 |
Where the Standard output and Actual Output are the same i.e. SO = AO, these figures can be obtained straightaway from the available data by building up the working table.
The standard is given for 80 units of output and the actual output achieved is also 80 units.
Where are these figures used?
The standard quantity and cost for actual output are useful in identifying
- The variance in labour/labor time used by comparing the actual labour/labor time used (168 hrs) and the standard labour/labor time (160 hrs). This variance valued at the standard wage rates gives what is called the "Labour/Labor Efficiency/Usage Variance".
- The variance in cost can be identified by comparing the actual cost (Rs. 2,100) and the standard cost (Rs. 1,920). This variance is what is called "Labour/Labor Cost Variance".
Why Recalculate Standards
Standards may be expressed for any level of activity. We may be required to recalculate the standards for a level of activity other than the one given. This recalculation may be based on (a) the actual output where we obtain the Standard Quantity for Actual Output and Standard Cost for Actual Output or (b) the actual input where we obtain the Standard Quantity for Actual Input and Standard Output for Actual Input.
Where Standard Output (SO) and Actual Output (AO) are not equal i.e. SO ≠ AO, we cannot obtain the variances by comparing the given data. In such a case we will have to recalculate the standards such that the AO and SO would be the same to enable us to derive variances by comparison.
|
Budgeted/Standard [Output : 500 units] |
Actual [Output : 400 units] |
|
Time (hrs) |
Rate (Rs/hr)
| Cost (Rs) |
Time (hrs) |
Rate (Rs/hr) |
Cost (Rs) |
| Operators |
1,000 |
12 |
12,000 |
880 |
12.50 |
11,000 |
From this data, is it appropriate to say that the production was achieved at a lesser cost? or that the labour/labor time had been used efficiently? Surely not. Why?
Because the actual labour/labor time utilised and the cost incurred is for manufacturing 400 units whereas the budget/standard is for manufacturing 500 units.
- Comparing the actual labour/labor time utilised for 400 units of output (880 hrs) with the standard labour/labor time for 500 units of output (1,000 kgs) and concluding that the labour/labor time utilised is very low is inappropriate.
- At the same time, comparing the actual labour/labor cost incurred for 400 units of output (Rs. 11,000) with the standard labour/labor cost of 500 units of output (Rs. 12,000) and concluding that the cost incurred is very low is also erroneous.
The comparison would be appropriate and meaningful if we compare
- The standard labour/labor time of 400 units which works out to 800 hrs {(1,000 ÷ 500) × 400} and the actual labour/labor time used.
- The standard labour/labor cost of 400 units which works out to Rs. 9,600 {(12,000 ÷ 500) × 400} and the actual cost of 400 units.
Therefore to find
- The variance in the labour/labor time used we need the standard time for actual output.
- The variance in the cost of labour/labor we need the standard cost for actual output.
Recollect that standards can be built for any production level. Standards may be expressed for either 1 unit of output, 2 units of output, ... to any production level. Recalculating standards implies drawing up the standards for a particular production level based on our calculation needs.
|
|
Formula » Standard Time for Actual Output
|
|
| |
Consider the following data arranged in a working table.
|
Standard [Production: 7,500 units] |
Actual [Production: 7,125 units] |
Time (hrs) |
Rate (Rs/hr)
| Cost (Rs) |
Rate (Rs/hr) |
Total |
Normal |
Abnromal |
Time (hrs) |
Cost (Rs) |
Time (hrs) |
Cost (Rs) |
Time (hrs) |
Cost (Rs) |
| Skilled |
200 |
20 |
4,000 |
22 |
240 |
5,280 |
216 |
4,752 |
24 |
528 |
| Semi Skilled |
400 |
15 |
6,000 |
14 |
500 |
7,000 |
450 |
6,300 |
50 |
700 |
| Un Skilled |
150 |
10 |
1,500 |
12 |
220 |
2,640 |
198 |
2,376 |
22 |
264 |
| Total
| 750 |
|
11,500 |
|
960 |
14,920 |
864 |
13,428 |
96 |
1,492 |
Note
The Working Table for Labour/Labor ≡ Working Table for Materials . However, where there is abnormal loss of time, you will notice that the actual data is segregated between net and idle times in case of labour/labor.
Standard Time for Actual Output
The logic behind the calculation and the formula for deriving the required time
For Each Labour/Labor type Separately
Logic
If the standard production of 7,500 units, the standard Time (Sk) is 200 hrs
If the standard production is 7,125 units, the Time (Sk) would be ??
| Standard Time (Sk) for an Output of 7,125 units |
| = |
| 7,125 units {Actual Output} | | 7,500 units {Standard Output} |
|
× 200 hrs {Standard Time (Sk)} |
|
Using the data given above,
|
Standard Time for Actual Output [ST for AO] for
| Skilled Workers |
= |
|
|
= |
0.95 × 200 hrs |
⇒ STSk for AO |
= |
190 hrs |
| Semi-Skilled Workers |
= |
|
|
= |
0.95 × 400 hrs |
⇒ STSe for AO |
= |
380 hrs |
| Unskilled Workers |
= |
|
|
= |
0.95 × 150 hrs |
⇒ SQC for AO |
= |
142.5 hrs |
|
Total |
|
712.5 hrs |
|
For All Labour/Labor Types Together
Logic
If the standard production of 7,500 units, the Standard Time is 750 hrs
If the standard production is 7,125 units, the Time would be ??
| Standard Time for an Output of 7,125 units |
| = |
| 7,125 units {Actual Output} | | 7,500 units {Standard Output} |
|
× 750 hrs {Standard Time (Standard Mix)} |
|
Using the data given above,
|
Standard Time for Actual Output [STMix for AO] for
| Total/All Labour/Labor types |
= |
|
|
= |
0.95 × 750 hrs |
⇒ STMix for AO |
= |
712.5 hrs |
|
Note:
The data from the actuals that is used in the above calculations is the Actual Output (AO) only. Thus, whether the actual data has abnormal loss time or not would not be relevant for these calculations.
|
|
Formula » Standard Cost for Actual Output
|
|
| |
Consider the following data arranged in a working table.
|
Standard [Production: 7,500 units] |
Actual [Production: 7,125 units] |
Time (hrs) |
Rate (Rs/hr)
| Cost (Rs) |
Rate (Rs/hr) |
Gross/Total |
Net |
Abnromal |
Time (hrs) |
Cost (Rs) |
Time (hrs) |
Cost (Rs) |
Time (hrs) |
Cost (Rs) |
| Skilled |
200 |
20 |
4,000 |
22 |
240 |
5,280 |
216 |
4,752 |
24 |
528 |
| Semi Skilled |
400 |
15 |
6,000 |
14 |
500 |
7,000 |
450 |
6,300 |
50 |
700 |
| Un Skilled |
150 |
10 |
1,500 |
12 |
220 |
2,640 |
198 |
2,376 |
22 |
264 |
| Total
| 750 |
|
11,500 |
|
960 |
14,920 |
864 |
13,428 |
96 |
1,492 |
Note
The Working Table for Labour/Labor ≡ Working Table for Materials . However, where there is abnormal loss of time, you will notice that the actual data is segregated between net and idle times in case of labour/labor.
Standard Cost for Actual Output
The logic behind the calculation and the formula for deriving the required cost
For each Labour/Labor type Separately
Standard Cost for Actual Output = Standard time for Actual Output × Standard Rate.
| ⇒ SCLab for AO |
= |
STLab for AO × SR |
| (Or) |
= |
|
| (Or) |
= |
|
|
[Useful where STLab for AO is already calculated] |
| [Useful where STLab, SRLab, SO, AO data is available] |
| [Useful where only SCLab, AO, SO data is available] |
Using the data in the above example,
|
Standard Cost for Actual Output [SC for AO] for
| Skilled Workers |
= |
|
|
= |
0.95 × Rs. 4,000 |
⇒ SCSk for AO |
= |
Rs. 3,800 |
| Semi-Skilled Workers |
= |
|
|
= |
0.95 × Rs. 6,000 |
⇒ SCSe for AO |
= |
Rs. 5,700 |
| Unskilled Workers |
= |
|
|
= |
0.95 × Rs. 1,500 |
⇒ SCUn for AO |
= |
Rs. 1,425 |
|
Total |
|
Rs. 10,925 |
|
For all Labour/Labor types together
Standard Cost of Standard Mix for Actual Output
= Standard time of Standard Mix for Actual Output × Standard Rate of Standard Mix.
| ⇒ SCMix for AO |
= |
STMix for AO × SRMix |
| (Or) |
= |
|
| (Or) |
= |
|
|
[Useful where STMix for AO is already calculated] |
| [Useful where STMix, SRMix, SO, AO data is available] |
| [Useful where only SCMix, AO, SO data is available] |
Using the data in the above example,
|
Standard Cost for Actual Output [SC for AO] for
| All Labour/Labor Types |
= |
|
|
0.95 × Rs. 11,500 |
⇒ SCMix for AO |
= |
Rs. 10,925 |
|
| Standard Rate of Mix |
= |
| Standard Cost of Mix | | Standard Time of Mix |
|
|
Using the data in the above example,
Note:
The data from the actuals that is used in the above calculations is the Actual Output (AO) only. Thus, whether the actual data has abnormal loss time or not would not be relevant for these calculations.
|
The above data (in the working table) with the recalculated standard would be.
|
Standard [Production: 7,125 units] |
Actual [Production: 7,125 units] |
Time (hrs) |
Rate (Rs/hr)
| Cost (Rs) |
Rate (Rs/hr) |
Total |
Normal |
Abnromal |
Time (hrs) |
Cost (Rs) |
Time (hrs) |
Cost (Rs) |
Time (hrs) |
Cost (Rs) |
| Skilled |
190 |
20 |
3,800 |
22 |
240 |
5,280 |
216 |
4,752 |
24 |
528 |
| Semi Skilled |
380 |
15 |
5,700 |
14 |
500 |
7,000 |
450 |
6,300 |
50 |
700 |
| Un Skilled |
142.5 |
10 |
1,425 |
12 |
220 |
2,640 |
198 |
2,376 |
22 |
264 |
| Total
| 712.5 |
|
10,925 |
|
960 |
14,920 |
864 |
13,428 |
96 |
1,492 |
By recalculating the standard for the actual output we would make the standard output and actual output in the recalculated data to be the same.
|
|