| ... From Page O:3 |
| Budget » Budgeted | |
|
A budget is a depiction of the future activity in quantitative terms. The budget may be for a particular period or a production process.
• Budgeted/Normal Activity
The activity that is budgeted to be achieved over the budgeted period or process is called Budgeted Activity. The activity may be measured in terms of output, input, labor/labour time worked, machine hours worked, etc. Since the budgeted activity would be the activity that should be achieved under normal circumstances, it is also called normal activity.
The two most common measures of budgeted activity that we deal with in analysing overhead variances are » Budgeted Output
The output that is budgeted to be achieved over the budgeted period or process.
This is the output that would have to be achieved if things go according to plans. » Budgeted Time
The time for which the production process is budgeted to be carried on over the budgeted period or process.
This is the time for which production process would have to be carried on if things go according to plans. • Budgeted (Overhead) Rates
The rates considered for absorption of overheads in preparing the budgets are what are called budgeted rates. These are nothing but the standard (pre-determined) rates of absorption of overheads (since budgets are always based on the standards).
The two types of absorption rates that we consider in variance analysis are » Budgeted Rate Per unit
Rate per unit would be interpreted as
» Budgeted Rate per hour (unit time)
Rate per hour (unit time) would be interpreted as
• Budgeted (Overhead) Cost
The amount of overhead cost that is budgeted to be incurred during a period or process i.e. for the Normal/Budgeted activity.
It is obtained as the product of the Budgeted Activity and the Budgeted Rate (i..e the Pre determined rate of absorption of overhead). » Budgeted Cost == Budgeted Output × Budgeted Rate per unit.
This is relevant when the overheads are being absorbed on per unit basis.
= Budgeted Time × Budgeted Rate per hour (unit time).
This is relevant when the overheads are being absorbed on per hour basis.
» Budgeted Overhead Cost would be interpreted as
|
| Actual » Incurred | |
• Actual Activity
This is the activity that is actually achieved during the production period or process. It may be measured in terms of output, input, labor/labour time worked, machine hours worked, etc.
The two most common measures of activity that we deal with in analysing overhead variances are » Actual Output
The output that has actually been achieved over the production period or process.
» Actual Time
The time for which the production process is actually carried on over the production period or process.
• Actual (Overhead) Cost » Incurred (Overhead) Expenditure
This is the actual overhead expenditure/cost incurred. This can be ascertained only after the incurrence of the cost i.e. at the end of the period or process in consideration.
The total overhead incurred is segregated into
• Where there are Semi-Variable Costs
If semi-variable overheads form a part of the total overhead cost/expenditure, it is segregated into two One a fixed part and the other a variable part.
Since there are no tools to analyse semi-variable overheads separately, we add up the fixed part of the expense to Fixed Overhead Cost and the variable part of the expense to the Variable Overhead Cost respectively, for the purpose of variance analysis. Therefore,
The actual overhead cost/expenditure incurred would be interpreted as
|
| Absorbed Overhead | |
|
Absorbed overhead is the amount of overhead cost that is absorbed into total cost based on the predetermined rates of absorption of overheads. The overhead absorbed is always dependent on the actual activity.
Overhead Absorbed = Actual time (No. of hours) worked × Overhead Absorption Rate (per hour) The overhead cost/expenditure absorbed would be interpreted as
There are other basis also for absorbing overheads. Since only the per unit and per hour basis are used extensively, we limit the discussion to these two bases only. |
| Finding absorbed overhead using a basis other than that used for absorption | |
|
The basis for absorption of overheads is something that is decided upon by the organisation based on a number of factors. Therefore, to know the amount of overhead absorbed we should know the basis of absorption that had been adopted.
This implies that
If we use a basis different from the one that had been used for absorbing overheads, the figure of absorbed overhead that we arrive at would be erroneous. However, there is a possibility to find the overhead absorbed using the per hour basis when they are absorbed on per unit basis and vice versa. Thus,
|
| Illustration » Problem + Working Notes | |
|
Consider the following data relating to a production process for a period.
• Working Notes» Budgeted Rate per unit
» Budgeted Rate per hour
|
| Illustration » Solution (Overheads Absorbed On per unit basis) | |
|
Calculating absorbed overhead based on
» Unit Rate
» Unit (time) hourly Rate
|
| Illustration » Solution (Overheads Absorbed On per hour basis) | |
|
Calculating absorbed overhead based on
» Unit (time) hourly Rate
» Unit Rate
|
| Author Credit : The Edifier | ... Continued Page O:5 |









