|
Fixed Overhead » Volume Variance = Calendar + Capacity + Efficiency : Variance
|
|
| |
The Fixed Overhead Volume variance which is the difference between the absorbed fixed overhead and budgeted fixed overhead is sub divided into three as fixed overhead Calendar variance, Fixed Overhead Capacity Variance and Fixed Overhead Efficiency Variance.
• Mathematical Derivation of the Constituents
Knowing how the volume variance is segregated into calendar, capacity and efficiency may aid your understand and recollection of the formulae.
Where
- FOHCA = Fixed Overhead Cost Absorbed
- BFOHC = Budgeted Fixed Overhead Cost
- FOHVolV = Fixed Overhead Volume Variance
- FOHCalV = Fixed Overhead Calendar Variance
- FOHCapV = Fixed Overhead Capacity Variance
- FOHEffV = Fixed Overhead Efficiency Variance
- SFOHC(T/O) = Standard Fixed Overhead Cost for Actual Activity (Time/Output)
- SFOHC(D) = Standard Fixed Overhead Cost for Actual Days
| Fixed Overhead Volume Variance |
= |
Fixed Overhead Absorbed − Budgeted Fixed Overhead |
| ⇒ FOHVolV |
= |
FOHCA − BFOHC |
|
= |
FOHCA − BFOHC + SFOHC(T) − SFOHC(T) + SFOHC(D) − SFOHC(D)
[Adding and deducting SFOHC(T/O) and SFOHC(D)]
|
|
= |
{FOHCA − SFOHC(T/O)} + {SFOHC(D) − BFOHC} + {SFOHC(T/O) − SFOHC(D)}
|
|
= |
FOHEffV + FOHCalV + FOHCapV |
|
= |
Efficiency Variance + Calendar Variance + Capacity Variance |
• Efficiency Variance
Thus,
| Fixed Overhead Efficiency Variance |
= |
Fixed Overhead Cost Absorbed
− Standard Fixed Overhead for Actual Activity (Time/Output) |
| ⇒ FOHEffV |
= |
FOHCA − SFOHC(T/O) |
• Calendar Variance
Thus,
| Fixed Overhead Calendar Variance |
= |
Standard Fixed Overhead Cost for Actual Days − Budgeted Fixed Overhead Cost |
| ⇒ FOHCalV |
= |
SFOHC(D) − BFOHC |
• Capacity Variance
Thus,
| Fixed Overhead Capacity Variance |
= |
Standard Fixed Overhead Cost for Actual (Time/Output) − Standard Fixed Overhead Cost for Actual Days |
| ⇒ FOHCapV |
= |
SFOHC(T/O) − SFOHC(D) |
Note
- Standard Fixed Overhead for Actual Days = Budgeted Fixed Overhead revised for the actual days worked.
- Standard Fixed Overhead for Actual Activity (Time/Output)
= Budgeted Fixed Overhead revised for the actual time worked (Or) actual output.
|
|
The Formulae » Fixed Overhead Efficiency Variance (FOHEffV)
|
|
| |
The Fixed overhead efficiency variance gives an idea of how much more or less the absorbed fixed overhead cost is when compared to the Standard Fixed Overheads for Actual Activity (Time or Output).
⇒ Fixed Overhead Efficiency Variance
= Fixed Overhead Cost Absorbed − Standard Fixed Overhead Cost for Actual Activity (Time/Output)
⇒ FOHEffV = FOHCA − SFOHC(T/O)
• Overheads Absorbed on Unit Rate Basis
| Standard Fixed Overhead Cost for Actual Activity (Time) |
= |
Budgeted Fixed Overhead Cost revised for Actual Time |
|
= |
|
|
× Budgeted Fixed Overhead Cost |
|
| SFOHC(T) |
= |
|
» Calculations based on Output (in Units)
| Fixed Overhead Cost Absorbed
|
= |
(Actual Output × Budgeted Rate/unit) |
| ⇒ FOHCA
|
= |
AO × BR/U |
| ⇒ FOHEffV
|
= |
FOHCA − SFOHC(T) |
|
= |
|
This can also be interpreted as
| ⇒ FOHEffV
|
= |
|
|
= |
| (AO × BR/U) − ( |
|
× (BO × BR/U) |
|
|
= |
|
» Calculations based on Input (Time in Hours)
| Fixed Overhead Cost Absorbed
|
= |
(Standard Time for Actual Output × Budgeted Rate/hour) |
| ⇒ FOHCA
|
= |
ST for AO × BR/H |
| (Or)
|
= |
|
| ⇒ FOHEffV
|
= |
FOHCA − SFOHC(T) |
|
= |
| ({AO × |
|
} × BR/hr) − ( |
|
× BFOH) |
|
This can also be interpreted as
| ⇒ FOHEffV
|
= |
| ({AO × |
|
} × BR/hr) − ( |
|
× BFOH) |
|
|
= |
| ( |
|
× BT × BR/hr) − ( |
|
× BFOH) |
|
|
= |
|
|
= |
|
• Overheads Absorbed on Time Basis
| Standard Fixed Overhead Cost for Actual Activity (Output) |
= |
Budgeted Fixed Overhead Cost revised for Actual Output |
|
= |
| Actual Output | | Budgeted Output |
|
× Budgeted Fixed Overhead Cost |
|
| SFOHC(O) |
= |
|
» Calculations based on Input (Time in Hours)
| Fixed Overhead Cost Absorbed
|
= |
(Actual Time × Budgeted Rate/hour) |
| ⇒ FOHCA
|
= |
(AT × BR/H) |
| ⇒ FOHEffV |
= |
FOHCA − SFOHC(O) |
|
= |
|
This can also be interpreted as
| ⇒ FOHEffV |
= |
|
|
= |
| (AT × BR/hr) − ( |
|
× BT × BR/hr) |
|
|
= |
|
» Calculations based on Output (In Units)
| Fixed Overhead Cost Absorbed
|
= |
(Standard Output for Actual Time × Budgeted Rate/Unit) |
| ⇒ FOHCA
|
= |
SO for AT × BR/U |
| (Or)
|
= |
|
| ⇒ FOHEffV |
= |
FOHCA − SFOHC(O) |
|
= |
| ({AT × |
|
} × BR/U) − ( |
|
× BFOH) |
|
This can also be interpreted as
| ⇒ FOHEffV |
= |
| ({AT × |
|
} × BR/U) − ( |
|
× BFOH) |
|
|
= |
| ( |
|
× BO × BR/U) − ( |
|
× BFOH) |
|
|
= |
|
|
= |
|
|
|
Efficiency Variance » Formula Interpretation
|
|
| |
A factory was to budgeted to produce 2,000 units of output @ one unit per 10 hours productive time working for 25 days. Rs. 40,000 of variable overhead cost and Rs. 80,000 of fixed overhead cost were budgeted to be incurred during that period.
The factory worked for 26 days putting in 860 hours work every day and achieved an output of 2,050 units. The expenditure incurred as overheads was Rs. 49,200 as variable overheads and Rs. 86,100 as fixed overheads.
What is the variation in total overhead cost on account of a variation in the efficiency of operations?
This information is provided by the fixed overhead capacity variance
|
The problem data arranged in a working table:
| Particulars |
Budgeted |
Actual |
|
a) Output
|
2,000 |
2,050 |
|
b) Working Days
|
25 |
26 |
|
c) Total Time Worked (in hrs)
|
20,000 |
22,360 |
|
d) Overhead Cost (in Rs.)
Variable
Fixed
Total
|
40,000 80,000 1,20,000
|
49,200 86,100 1,35,300
|
|
e) Overhead Rates [(d) ÷ (a)] (in Rs./Unit)
Variable [(40,000 ÷ 2,000)]
Fixed [(80,000 ÷ 2,000)]
Total [(1,20,000 ÷ 2,000)]
|
20 40 60
|
|
|
f) Overhead Rates [(d) ÷ (c)] (in Rs./hr)
Variable [(40,000 ÷ 20,000)]
Fixed [(80,000 ÷ 20,000)]
Total [(1,20,000 ÷ 20,000)]
|
2 4 6
|
|
• Note
This working table gives all the data that would be needed to solve a problem involving all overhead variances. In Calculating only the total overhead cost variance you may not need all that data.
We give it here so that you get accustomed to preparing the working table by the time you complete going through all the overhead variances.
|
• Working Time
» Budgeted Time [BT]
| BT |
= |
Budgeted Output × Budgeted Time/unit |
|
= |
2,000 units × 10 labor/labour hrs/unit
[@ one unit per 10 hours productive time]
|
|
= |
20,000 labor/labour hrs |
» Actual Time [AT]
| AT |
= |
Number of Days × Actual Time/day |
|
= |
26 days × 860 labour/labor hrs/day |
|
= |
22,360 labor/labour hrs |
|
|
Solution [Overheads Absorbed on Unit basis]
|
|
| |
| Standard Fixed Overhead Cost for Actual Activity (Time) |
= |
|
|
× Budgeted Fixed Overhead Cost |
|
| SFOHC(T) |
= |
|
|
= |
|
|
= |
Rs. 1.118 × 80,000 |
|
= |
Rs. 89,440 |
» Calculations Based on Output (in Units)
| Fixed Overhead Cost Absorbed
|
= |
(Actual Output × Budgeted Rate/unit) |
| ⇒ FOHCA
|
= |
AO × BR/U |
|
= |
2,050 units × Rs. 40/unit |
|
= |
Rs. 82,000 |
» Calculations Based on Input (Time in Hours)
| Fixed Overhead Cost Absorbed
|
= |
(Standard Time for Actual Output × Budgeted Rate/hour) |
| ⇒ FOHCA
|
= |
|
|
= |
| {2,050 units × |
|
} × Rs. 4/hour |
|
|
= |
Rs. 2,050 × 10 × 4 |
|
= |
Rs. 82,000 |
• Calculation of Variance
| FOHEffV |
= |
FOHCA − SFOHC(T) |
|
= |
Rs. 82,000 − Rs. 89,440 |
|
= |
− Rs. 7,440 [Adv] |
|
|
Solution [Overheads Absorbed on Time basis]
|
|
| |
| Standard Fixed Overhead Cost for Actual Activity (Output) |
= |
| Actual Output | | Budgeted Output |
|
× Budgeted Fixed Overhead Cost |
|
| SFOHC(O) |
= |
|
|
= |
|
|
= |
Rs. 1.025 × 80,000 |
|
= |
Rs. 82,000 |
» Calculations Based on Input (Time in Hours)
| Fixed Overhead Cost Absorbed
|
= |
(Actual Time × Budgeted Rate/hour) |
| ⇒ FOHCA
|
= |
(AT × BR/H) |
|
= |
22,360 hours × Rs. 4/hour |
|
= |
Rs. 89,440 |
» Calculations Based on Output (in Units)
| Fixed Overhead Cost Absorbed
|
= |
(Standard Output for Actual Time × Budgeted Rate/Unit) |
| ⇒ FOHCA
|
= |
|
|
= |
| {22,360 hours × |
|
} × Rs. 40/unit |
|
|
= |
Rs. 22,360 × 0.1 × 40 |
|
= |
Rs. 89,440 |
• Calculation of Variance
| FOHEffV |
= |
FOHCA − SFOHC(O) |
|
= |
Rs. 89,440 − Rs. 82,000 |
|
= |
+ Rs. 7,440 [Fav] |
|
|
Formulae using Inter-relationships among Variances
|
|
| |
- FOHVolV = FOHEffV + FOHCalV + FOHCapV → (1)
From (1)
|
FOHEffV = FOHVolV − FOHCalV − FOHCapV
|
• Verification
The interrelationships between variances would also be useful in verifying whether our calculations are correct or not. After calculating the two fixed overhead variances we can verify whether FOHExpV and FOHVolV add up to FOHCV or not. If FOHExpV + FOHVolV = FOHCV we can assume our calculations to be correct.
» Overheads Absorbed on Unit Basis
| FOHEffV + FOHCalV + FOHCapV |
= |
(− Rs. 7,440) + (+ Rs. 3,200) + (+ Rs. 6,240) |
|
= |
+ Rs. 2,000 [Fav] |
|
= |
FOHVolV → TRUE |
» Overheads Absorbed on Time Basis
| FOHEffV + FOHCalV + FOHCapV |
= |
(+ Rs. 7,440) + (+ Rs. 3,200) + (− Rs. 1,200) |
|
= |
+ Rs. 9,440 [Fav] |
|
= |
FOHVolV → TRUE |
|
|
|