Fixed Overhead Volume Variance
Illustration - Problem
The factory worked for 26 days putting in 860 hours work every day and achieved an output of 2,050 units. The expenditure incurred as overheads was 49,200 towards variable overheads and 86,100 towards fixed overheads.
Calculate overhead variances
Standard | Actual | Absorbed | ||||
---|---|---|---|---|---|---|
Budgeted | for AO | for AI | for AP | |||
A | B | C | ||||
a) Output (units) b) Days c) Time (hrs) d) Overhead Cost 1) Variable 2) Fixed 3) Total | 2,000 25 40,000 80,000 1,20,000 | 2,050 26 49,200 86,100 1,35,300 |
The working table is populated with the information that can be obtained as it is from the problem data. The rest of the information that is present in a full fledged working table that we make use of in problem solving is filled below.
Formulae - Fixed Overhead Volume Variance ~ FOHVOLV
Fixed Overhead Volume Variance is the difference between the absorbed fixed overhead cost and the standard fixed overhead cost for actual output.
⇒ Fixed Overhead Volume Variance (FOHVOLV)
= | AbC − BC Absorbed Cost − Budgeted Cost |
Absorbed Cost (Fixed Overhead)
In problem solving absorbed cost may be provided as a calculated figure. In such a case we do not get concerned about the rate of absorption unless specifically needed in some calculation.Where the absorbed cost is not known we may have to calculate the cost. This calculation is based on the rate of absorption that has been used in the context to absorb total overheads.
Absorption based on output (units)
Absorbed Cost ~ AbC
= AO × AbR/UO Or = SI(AO) × AbR/UI Or = SP(AO) × AbR/UP Absorption based on inputs
Absorbed Cost ~ AbC
= AI × AbR/UI Or = SO(AI) × AbR/UO Or = SP(AI) × AbR/UP Absorption based on periods
Absorbed Cost ~ AbC
= AP × AbR/UP Or = SO(AP) × AbR/UO Or = SI(AP) × AbR/UI
Budgeted Cost (Fixed Overhead)
In problem solving the budgeted fixed cost is generally provided as a calculated figure.
Where the budgeted cost is not known we may have to calculate the cost. This calculation requires a measure of budgeted activity and the relevant rate.
Budgeted Cost ~ BC(F)
= | BO × BR/UO | |
Or | = | BI × BR/UI |
Or | = | BP × BR/UP |
Formula in useful forms
FOHVOLV | = | AbC − BC Absorbed Cost − Budgeted Cost |
Note
- BC, BR/UO, BR/UT, BR/D in the above calculations pertains to fixed overheads.
- Theoretically there are many possibilities. Only those that provide peculiar routes to solve problems are given as an academic exercise.
- Finding the costs by building up the working table and using the formula involving costs is the simplest way to find the FOHVOLV.
Solution - (Assuming absorption is based on Output)
Standard | Actual | Absorbed | ||||
---|---|---|---|---|---|---|
Budgeted | for AO | for AI | for AP | |||
A | B | C | ||||
I) Factor | 1.025 | |||||
a) Output (units) b) Periods (Days) c) Time (hrs) d) Overhead Cost 1) Variable e) Overhead Rate (/Unit) 2) Fixed 3) Total 1) Variable 2) Fixed 3) Total (d1) ÷ (a) (d2) ÷ (a) (d3) ÷ (a) 1) Variable 2) Fixed 3) Total (d1) ÷ (c) (d2) ÷ (c) (d3) ÷ (c) 1) Variable 2) Fixed 3) Total (d1) ÷ (b) (d2) ÷ (b) (d3) ÷ (b) | 2,000 25 20,000 40,000 80,000 1,20,000 40 4 3,200 | 25.625 20,500 | 2,050 26 22,360 49,200 86,100 1,35,300 | 82,000 =BR =BR =BR |
In the absence of information to the contrary we assume
AbR/UO(F) | = | BR/UO(F) |
= | 40 |
Absorbed Fixed Overhead Cost ~ AbC(F)
= | AO × AbR/UO(F) |
= | 2,050 units × 40/unit |
= | 82,000 |
Fixed Overhead Volume Variance
VOHVOLV | = | AbC − BC |
= | 82,000 − 80,000 | |
= | + 2,000 [Fav] |
Alternatives
There are no direct formulae for calculating Fixed overhead volume variance. The alternatives given below pertain to calculating the absorbed overhead in an alternative manner.(AO) | = |
| ||
= |
| |||
= | 1.025 |
Calculations based on input (time)
The absorbed overhead may be ascertained using the data relating to input.Standard input (time) for actual output and the overhead absorption rate per unit input are required for such a calculation.
One unit per 10 hours productive time
⇒ Budgeted Time per unit = 10 hours
Total Budgeted Time
= Budgeted Output × Budgeted Time/unit = 2,000 units × 10 hrs/unit = 20,000 hrs Total Actual Time
= Number of Days × Actual Time/day = 26 days × 860 hrs/day = 22,360 labor/labour hrs ST(AO) = BT × AO BO = 20,000 hrs × 1.025 = 20,500 hrs In the absence of information to the contrary we assume
AbR/UT(F) = BR/UT(F) = 4 Absorbed Variable Overhead Cost ~ AbC(V)
= ST(AO) × AbR/UT(V) = 20,500 hrs × 4/hr = 82,000 Calculations based on periods (days)
The absorbed overhead may be ascertained using the data relating to periods, days in this case.Standard periods (days) for actual output and the overhead absorption rate per unit period (day) are required for such a calculation.
SD(AO) = BD × AO BO = 25 days × 1.025 = 25.625 days In the absence of information to the contrary we assume
AbR/D(F) = BR/D(F) = 3,200 Absorbed Variable Overhead Cost ~ AbC(F)
= SD(AO) × AbR/D(V) = 25.625 days × 3,200/day = 82,000
Building the working table with all the values needed and then using the formula based on values would be the simplest method to arrive at the value of the variance.
The method of absorption adopted and the method of calculation adopted would influence the calculation of the overhead absorbed only.
Solution - (Assuming absorption is based on Input [time])
Standard | Actual | Absorbed | ||||
---|---|---|---|---|---|---|
Budgeted | for AO | for AI | for AP | |||
A | B | C | ||||
I) Factor | 1.118 | |||||
a) Output (units) b) Periods (Days) c) Time (hrs) d) Overhead Cost 1) Variable e) Overhead Rate (/Unit) 2) Fixed 3) Total 1) Variable 2) Fixed 3) Total (d1) ÷ (a) (d2) ÷ (a) (d3) ÷ (a) 1) Variable 2) Fixed 3) Total (d1) ÷ (c) (d2) ÷ (c) (d3) ÷ (c) 1) Variable 2) Fixed 3) Total (d1) ÷ (b) (d2) ÷ (b) (d3) ÷ (b) | 2,000 25 20,000 40,000 80,000 1,20,000 40 4 3,200 | 2,236 27.95 | 2,050 26 22,360 49,200 86,100 1,35,300 | 89,440 =BR =BR =BR |
One unit per 10 hours productive time
⇒ Budgeted Time per unit = 10 hours
Total Budgeted Time
= | Budgeted Output × Budgeted Time/unit |
= | 2,000 units × 10 hrs/unit |
= | 20,000 hrs |
Total Actual Time
= | Number of Days × Actual Time/day |
= | 26 days × 860 hrs/day |
= | 22,360 labor/labour hrs |
In the absence of information to the contrary we assume
AbR/UT(T) | = | BR/UT(T) |
= | 4/hr |
Absorbed Fixed Overhead Cost ~ AbC(F)
= | AO × AbR/UT(T) |
= | 22,360 hrs × 4/hr |
= | 89,440 |
Fixed Overhead Volume Variance
FOHVOLV | = | AbC − BC |
= | 89,440 − 80,000 | |
= | + 9,440 [Fav] |
Alternatives
Apart from the basic formula based on costs, there are no alternative formulae for calculating Fixed overhead volume variance.The alternatives given below pertain to calculating the absorbed overhead in an alternative manner.
(AT) | = |
| ||
= |
| |||
= | 1.118 |
Calculations based on output
The absorbed overhead may be ascertained using the data relating to output.Standard output for actual input (time) and the overhead absorption rate per unit output are required for such a calculation.
SO(AT) = BO × AT BT = 2,000 units × 1.118 = 2,236 units In the absence of information to the contrary we assume
AbR/UO(T) = BR/UO(T) = 40 Absorbed Fixed Overhead Cost ~ AbC(T)
= SO(AT) × AbR/U(T) = 2,236 units × 40/unit = 89,440 Calculations based on periods (days)
The absorbed overhead may be ascertained using the data relating to periods, days in this case.Standard periods (days) for actual output and the overhead absorption rate per unit period (day) are required for such a calculation.
SD(AT) = BD × AT BT = 25 days × 1.118 = 27.95 days In the absence of information to the contrary we assume
AbR/D(T) = BR/D(T) = 3,200 Absorbed Fixed Overhead Cost ~ AbC(F)
= SD(AO) × AbR/D(T) = 27.95 days × 3,200/day = 89,440
Building the working table with all the values needed and then using the formula based on values would be the simplest method to arrive at the value of the variance.
The method of absorption adopted and the method of calculation adopted would influence the calculation of the overhead absorbed only.
Solution - (Assuming absorption is based on Periods [days])
Standard | Actual | Absorbed | ||||
---|---|---|---|---|---|---|
Budgeted | for AO | for AI | for AP | |||
A | B | C | ||||
I) Factor | 1.04 | |||||
a) Output (units) b) Periods (Days) c) Time (hrs) d) Overhead Cost 1) Variable e) Overhead Rate (/Unit) 2) Fixed 3) Total 1) Variable 2) Fixed 3) Total (d1) ÷ (a) (d2) ÷ (a) (d3) ÷ (a) 1) Variable 2) Fixed 3) Total (d1) ÷ (c) (d2) ÷ (c) (d3) ÷ (c) 1) Variable 2) Fixed 3) Total (d1) ÷ (b) (d2) ÷ (b) (d3) ÷ (b) | 2,000 25 20,000 40,000 80,000 1,20,000 40 4 3,200 | 2,080 20,800 | 2,050 26 49,200 86,100 1,35,300 | 83,200 =BR =BR =BR |
In the absence of information to the contrary we assume
AbR/UT(T) | = | BR/UT(T) |
= | 3,200/day |
Absorbed Fixed Overhead Cost ~ AbC(F)
= | AD × AbR/D(F) |
= | 26 days × 3,200/day |
= | 83,200 |
Fixed Overhead Volume Variance
FOHVOLV | = | AbC − BC |
= | 83,200 − 80,000 | |
= | + 3,200 [Fav] |
Alternatives
There are no direct formulae for calculating Fixed overhead volume variance. The alternatives given below pertain to calculating the absorbed overhead in an alternative manner.(AD) | = |
| ||
= |
| |||
= | 1.04 |
Calculations based on inputs (time)
The absorbed overhead may be ascertained using the data relating to input (time).Standard input (time) for actual periods (days) and the overhead absorption rate per unit input are required for such a calculation.
One unit per 10 hours productive time
⇒ Budgeted Time per unit = 10 hours
Total Budgeted Time
= Budgeted Output × Budgeted Time/unit = 2,000 units × 10 hrs/unit = 20,000 hrs Total Actual Time
= Number of Days × Actual Time/day = 26 days × 860 hrs/day = 22,360 labor/labour hrs ST(AD) = BT × AD BD = 20,000 hrs × 1.04 = 20,800 hrs In the absence of information to the contrary we assume
AbR/UT(F) = BR/UT(F) = 4 Absorbed Fixed Overhead Cost ~ AbC(F)
= ST(AD) × AbR/UT(F) = 20,800 hrs × 4/hr = 83,200 Calculations based on output
The absorbed overhead may be ascertained using the data relating to output.Standard output for actual periods (days) and the overhead absorption rate per unit output are required for such a calculation.
SO(AD) = BO × AD BD = 2,000 units × 1.04 = 2,080 units In the absence of information to the contrary we assume
AbR/UO(F) = BR/UO(F) = 40 Absorbed Fixed Overhead Cost ~ AbC(F)
= SO(AD) × AbR/UO(F) = 2,080 units × 40/unit = 83,200
Building the working table with all the values needed and then using the formula based on values would be the simplest method to arrive at the value of the variance.
The method of absorption adopted and the method of calculation adopted would influence the calculation of the overhead absorbed only.
Fixed Overhead Volume Variance - Miscellaneous Aspects
Nature of Variance
Based on the relations derived from the formulae for calculating FOHVOLV, we can identify the nature of Variance
- AbC ___ BC
The variance would be
- zero when =
- Positive when >
- Negative when <
Interpretation of the Variance
The following interpretations may be made
No Variance
The absorbed fixed overhead cost is the same as the budgeted costFavourable/Favorable
The absorbed fixed overhead cost is greater than the budgeted costAdverse
The absorbed fixed overhead cost is lesser than the budgeted costWho is answerable for the Variance?
Fixed Overhead Volume Variance represents the gain or loss on account of putting the production facility to use to a greater/lesser extent. Those who are responsible for putting the production facility to use would be made answerable for the variance.Reasons for variance can be further specified
The fixed overhead volume variance would only let us know that the production facility has been put to use to a greater/lesser extent than planned/budgeted. It does not help us answer specific questions relating to the variance like, is it on account of the variation in the periods worked or the inputs used or efficiency.Taking the data from the above illustration, we can notice that variance in fixed overhead cost may be on account of
- The actual overhead incurrence rate per unit time/output being different from the budgeted rate.
Overhead Rate per unit - Actual 22 to 20 budgeted.
Overhead Rate per unit time - Actual 2.02 to 2 budgeted.
- The rate at which the output has been achieved is different from the budgeted rate.
Time per unit output - 10.91 actual to 10 budgeted.
Standard Actual Absorbed Budgeted for AO for AI for AP A B C a) Output (units)
b) Periods (Days)
c) Time (hrs)
d) Overhead Cost
...
g) Time/unit(hrs) (c) ÷ (a)2,000
25
20,000
102,050
26
22,360
10.91The actual time per unit shown as 10.91 is an approximation of2,236 205
This specific identification can be obtained by breaking down the variance into its constituent parts.
- The actual overhead incurrence rate per unit time/output being different from the budgeted rate.
Constituents of Fixed Overhead Volume Variance
FOHVOLV | = | AbC − BC |
Adding and deduct SC(AO), SC(AI) and SC(AP) on the RHS | ||
= | AbC − BC + SC(AO) − SC(AO) + SC(AI) − SC(AI) + SC(AP) − SC(AP) | |
= | AbC − SC(AO) + SC(AO) − SC(AI) + SC(AP) − BC + SC(AI) − SC(AP) | |
= | [AbC − SC(AO)] + [SC(AO) − SC(AI)] + [SC(AP) − BC] + [SC(AI) − SC(AP)] | |
Taking time as input and days as periods | ||
= | [AbC − SC(AO)] + [SC(AO) − SC(AT)] + [SC(AD) − BC] + [SC(AT) − SC(AD)] | |
= | Absorption Variance + Efficiency Variance + Calendar Variance + Capacity Variance | |
= | FOHABSV + FOHEFFV + FOHCALV + FOHCAPV |
Alternative
Where the overheads are being absorbed based on output and the budgeted rate is the absorption rate, then AbC = SC(AO).In such a case the Absorption Variance does not exist and the Fixed Overhead Volume Variance may be divided into only three component parts, the capacity, calendar and efficiency variances.
FOHVOLV | = | AbC − BC |
Adding and deduct SC(AI) and SC(AP) on the RHS | ||
= | AbC − BC + SC(AI) − SC(AI) + SC(AP) − SC(AP) | |
= | AbC − SC(AI) + SC(AP) − BC + SC(AI) − SC(AP) | |
= | [AbC − SC(AI)] + [SC(AP) − BC] + [SC(AI) − SC(AP)] | |
Taking time as input and days as periods | ||
= | [AbC − SC(AT)] + [SC(AD) − BC] + [SC(AT) − SC(AD)] | |
= | Efficiency Variance + Calendar Variance + Capacity Variance | |
= | FOHEFFV + FOHCALV + FOHCAPV |
The only difference is in the terms that appear in the formula for efficiency variance and the absence of absorption variance. Absorbed cost (AbC) replaces standard cost of actual output [SC(AO)] in the formula for efficiency variance.
Formulae using Inter-relationships among Variances
- FOHVOLV = FOHCV − FOHEXPV
- FOHVOLV = FOHABSV + FOHCAPV + FOHCALV + FOHEFFV
Verification
The interrelationships between variances would also be useful in verifying whether our calculations are correct or not.Basis of Absorption | |||
---|---|---|---|
Output | Input (Time) | Periods (Days) | |
VOHABSV + VOHEFFV + VOHEXPV | 0 − 3,720 − 4,480 | + 3,720 − 3,720 − 4,480 | + 600 − 3,720 − 4,480 |
a) VOHCV | − 8,200 | − 4,480 | − 7,600 |
FOHCALV + FOHCAPV + FOHEFV | — — — | — — — | — — — |
FOHVOLV FOHEXPV | + 2,000 — | + 9,440 — | + 3,200 — |
b) FOHCV | − 4,100 | + 3,340 | − 2,900 |
TOHCV (a) + (b) | − 12,300 | − 1,140 | − 10,500 |
To enable understanding we have worked out the illustration under the three possible scenarios of overhead being absorbed on output, input and period basis.
Please be aware that only one of these methods would be in use.