Fixed Overhead Volume Variance

Illustration - Problem

A factory was budgeted to produce 2,000 units of output @ one unit per 10 hours productive time working for 25 days. 40,000 for variable overhead cost and 80,000 for fixed overhead cost were budgeted to be incurred during that period.

The factory worked for 26 days putting in 860 hours work every day and achieved an output of 2,050 units. The expenditure incurred as overheads was 49,200 towards variable overheads and 86,100 towards fixed overheads.

Calculate overhead variances

Working Table
Standard Actual Absorbed
Budgeted for AO for AI for AP
A B C
a) Output (units)
b) Days
c) Time (hrs)
d) Overhead Cost
1) Variable
2) Fixed
3) Total
2,000
25


40,000
80,000
1,20,000
2,050
26


49,200
86,100
1,35,300

The working table is populated with the information that can be obtained as it is from the problem data. The rest of the information that is present in a full fledged working table that we make use of in problem solving is filled below.

Formulae - Fixed Overhead Volume Variance ~ FOHVOLV

Is the absorbed fixed overhead cost different from the budgeted fixed overhead cost?

Fixed Overhead Volume Variance is the difference between the absorbed fixed overhead cost and the standard fixed overhead cost for actual output.

⇒ Fixed Overhead Volume Variance (FOHVOLV)

= AbC − BC

Absorbed Cost − Budgeted Cost

Absorbed Cost (Fixed Overhead)

In problem solving absorbed cost may be provided as a calculated figure. In such a case we do not get concerned about the rate of absorption unless specifically needed in some calculation.

Where the absorbed cost is not known we may have to calculate the cost. This calculation is based on the rate of absorption that has been used in the context to absorb total overheads.

  • Absorption based on output (units)

    Absorbed Cost ~ AbC

    = AO × AbR/UO
    Or = SI(AO) × AbR/UI
    Or = SP(AO) × AbR/UP
  • Absorption based on inputs

    Absorbed Cost ~ AbC

    = AI × AbR/UI
    Or = SO(AI) × AbR/UO
    Or = SP(AI) × AbR/UP
  • Absorption based on periods

    Absorbed Cost ~ AbC

    = AP × AbR/UP
    Or = SO(AP) × AbR/UO
    Or = SI(AP) × AbR/UI

Budgeted Cost (Fixed Overhead)

In problem solving the budgeted fixed cost is generally provided as a calculated figure.

Where the budgeted cost is not known we may have to calculate the cost. This calculation requires a measure of budgeted activity and the relevant rate.

Budgeted Cost ~ BC(F)

= BO × BR/UO
Or = BI × BR/UI
Or = BP × BR/UP

Formula in useful forms

FOHVOLV = AbC − BC

Absorbed Cost − Budgeted Cost

Note

  • BC, BR/UO, BR/UT, BR/D in the above calculations pertains to fixed overheads.
  • Theoretically there are many possibilities. Only those that provide peculiar routes to solve problems are given as an academic exercise.
  • Finding the costs by building up the working table and using the formula involving costs is the simplest way to find the FOHVOLV.

Solution - (Assuming absorption is based on Output)

Standard Actual Absorbed
Budgeted for AO for AI for AP
A B C
I) Factor 1.025
a) Output (units)
b) Periods (Days)
c) Time (hrs)
d) Overhead Cost
1) Variable
2) Fixed
3) Total
e) Overhead Rate (/Unit)
1) Variable
2) Fixed
3) Total
(d1) ÷ (a)
(d2) ÷ (a)
(d3) ÷ (a)
f) Overhead Rate (/Unit Time)
1) Variable
2) Fixed
3) Total
(d1) ÷ (c)
(d2) ÷ (c)
(d3) ÷ (c)
g) Overhead Rate (/Unit Period)
1) Variable
2) Fixed
3) Total
(d1) ÷ (b)
(d2) ÷ (b)
(d3) ÷ (b)
2,000
25
20,000

40,000
80,000
1,20,000


40



4



3,200

25.625
20,500




2,050
26
22,360

49,200
86,100
1,35,300
















82,000



=BR



=BR



=BR

In the absence of information to the contrary we assume

AbR/UO(F) = BR/UO(F)
= 40

Absorbed Fixed Overhead Cost ~ AbC(F)

= AO × AbR/UO(F)
= 2,050 units × 40/unit
= 82,000

Fixed Overhead Volume Variance

VOHVOLV = AbC − BC
= 82,000 − 80,000
= + 2,000 [Fav]

Alternatives

There are no direct formulae for calculating Fixed overhead volume variance. The alternatives given below pertain to calculating the absorbed overhead in an alternative manner.
(AO) =
AO
BO
=
2,050 units
2,000 units
= 1.025
  • Calculations based on input (time)

    The absorbed overhead may be ascertained using the data relating to input.

    Standard input (time) for actual output and the overhead absorption rate per unit input are required for such a calculation.

    One unit per 10 hours productive time

    ⇒ Budgeted Time per unit = 10 hours

    Total Budgeted Time

    = Budgeted Output × Budgeted Time/unit
    = 2,000 units × 10 hrs/unit
    = 20,000 hrs

    Total Actual Time

    = Number of Days × Actual Time/day
    = 26 days × 860 hrs/day
    = 22,360 labor/labour hrs
    ST(AO) = BT ×
    AO
    BO
    = 20,000 hrs × 1.025
    = 20,500 hrs

    In the absence of information to the contrary we assume

    AbR/UT(F) = BR/UT(F)
    = 4

    Absorbed Variable Overhead Cost ~ AbC(V)

    = ST(AO) × AbR/UT(V)
    = 20,500 hrs × 4/hr
    = 82,000
  • Calculations based on periods (days)

    The absorbed overhead may be ascertained using the data relating to periods, days in this case.

    Standard periods (days) for actual output and the overhead absorption rate per unit period (day) are required for such a calculation.

    SD(AO) = BD ×
    AO
    BO
    = 25 days × 1.025
    = 25.625 days

    In the absence of information to the contrary we assume

    AbR/D(F) = BR/D(F)
    = 3,200

    Absorbed Variable Overhead Cost ~ AbC(F)

    = SD(AO) × AbR/D(V)
    = 25.625 days × 3,200/day
    = 82,000

Building the working table with all the values needed and then using the formula based on values would be the simplest method to arrive at the value of the variance.

The method of absorption adopted and the method of calculation adopted would influence the calculation of the overhead absorbed only.

Solution - (Assuming absorption is based on Input [time])

Standard Actual Absorbed
Budgeted for AO for AI for AP
A B C
I) Factor 1.118
a) Output (units)
b) Periods (Days)
c) Time (hrs)
d) Overhead Cost
1) Variable
2) Fixed
3) Total
e) Overhead Rate (/Unit)
1) Variable
2) Fixed
3) Total
(d1) ÷ (a)
(d2) ÷ (a)
(d3) ÷ (a)
f) Overhead Rate (/Unit Time)
1) Variable
2) Fixed
3) Total
(d1) ÷ (c)
(d2) ÷ (c)
(d3) ÷ (c)
g) Overhead Rate (/Unit Period)
1) Variable
2) Fixed
3) Total
(d1) ÷ (b)
(d2) ÷ (b)
(d3) ÷ (b)
2,000
25
20,000

40,000
80,000
1,20,000


40



4



3,200
2,236
27.95





2,050
26
22,360

49,200
86,100
1,35,300
















89,440



=BR



=BR



=BR

One unit per 10 hours productive time

⇒ Budgeted Time per unit = 10 hours

Total Budgeted Time

= Budgeted Output × Budgeted Time/unit
= 2,000 units × 10 hrs/unit
= 20,000 hrs

Total Actual Time

= Number of Days × Actual Time/day
= 26 days × 860 hrs/day
= 22,360 labor/labour hrs

In the absence of information to the contrary we assume

AbR/UT(T) = BR/UT(T)
= 4/hr

Absorbed Fixed Overhead Cost ~ AbC(F)

= AO × AbR/UT(T)
= 22,360 hrs × 4/hr
= 89,440

Fixed Overhead Volume Variance

FOHVOLV = AbC − BC
= 89,440 − 80,000
= + 9,440 [Fav]

Alternatives

Apart from the basic formula based on costs, there are no alternative formulae for calculating Fixed overhead volume variance.

The alternatives given below pertain to calculating the absorbed overhead in an alternative manner.

(AT) =
AT
BT
=
22,360 hrs
20,000 hrs
= 1.118
  • Calculations based on output

    The absorbed overhead may be ascertained using the data relating to output.

    Standard output for actual input (time) and the overhead absorption rate per unit output are required for such a calculation.

    SO(AT) = BO ×
    AT
    BT
    = 2,000 units × 1.118
    = 2,236 units

    In the absence of information to the contrary we assume

    AbR/UO(T) = BR/UO(T)
    = 40

    Absorbed Fixed Overhead Cost ~ AbC(T)

    = SO(AT) × AbR/U(T)
    = 2,236 units × 40/unit
    = 89,440
  • Calculations based on periods (days)

    The absorbed overhead may be ascertained using the data relating to periods, days in this case.

    Standard periods (days) for actual output and the overhead absorption rate per unit period (day) are required for such a calculation.

    SD(AT) = BD ×
    AT
    BT
    = 25 days × 1.118
    = 27.95 days

    In the absence of information to the contrary we assume

    AbR/D(T) = BR/D(T)
    = 3,200

    Absorbed Fixed Overhead Cost ~ AbC(F)

    = SD(AO) × AbR/D(T)
    = 27.95 days × 3,200/day
    = 89,440

Building the working table with all the values needed and then using the formula based on values would be the simplest method to arrive at the value of the variance.

The method of absorption adopted and the method of calculation adopted would influence the calculation of the overhead absorbed only.

Solution - (Assuming absorption is based on Periods [days])

Standard Actual Absorbed
Budgeted for AO for AI for AP
A B C
I) Factor 1.04
a) Output (units)
b) Periods (Days)
c) Time (hrs)
d) Overhead Cost
1) Variable
2) Fixed
3) Total
e) Overhead Rate (/Unit)
1) Variable
2) Fixed
3) Total
(d1) ÷ (a)
(d2) ÷ (a)
(d3) ÷ (a)
f) Overhead Rate (/Unit Time)
1) Variable
2) Fixed
3) Total
(d1) ÷ (c)
(d2) ÷ (c)
(d3) ÷ (c)
g) Overhead Rate (/Unit Period)
1) Variable
2) Fixed
3) Total
(d1) ÷ (b)
(d2) ÷ (b)
(d3) ÷ (b)
2,000
25
20,000

40,000
80,000
1,20,000


40



4



3,200
2,080

20,800




2,050
26


49,200
86,100
1,35,300
















83,200



=BR



=BR



=BR

In the absence of information to the contrary we assume

AbR/UT(T) = BR/UT(T)
= 3,200/day

Absorbed Fixed Overhead Cost ~ AbC(F)

= AD × AbR/D(F)
= 26 days × 3,200/day
= 83,200

Fixed Overhead Volume Variance

FOHVOLV = AbC − BC
= 83,200 − 80,000
= + 3,200 [Fav]

Alternatives

There are no direct formulae for calculating Fixed overhead volume variance. The alternatives given below pertain to calculating the absorbed overhead in an alternative manner.
(AD) =
AD
BD
=
26 days
25 days
= 1.04
  • Calculations based on inputs (time)

    The absorbed overhead may be ascertained using the data relating to input (time).

    Standard input (time) for actual periods (days) and the overhead absorption rate per unit input are required for such a calculation.

    One unit per 10 hours productive time

    ⇒ Budgeted Time per unit = 10 hours

    Total Budgeted Time

    = Budgeted Output × Budgeted Time/unit
    = 2,000 units × 10 hrs/unit
    = 20,000 hrs

    Total Actual Time

    = Number of Days × Actual Time/day
    = 26 days × 860 hrs/day
    = 22,360 labor/labour hrs
    ST(AD) = BT ×
    AD
    BD
    = 20,000 hrs × 1.04
    = 20,800 hrs

    In the absence of information to the contrary we assume

    AbR/UT(F) = BR/UT(F)
    = 4

    Absorbed Fixed Overhead Cost ~ AbC(F)

    = ST(AD) × AbR/UT(F)
    = 20,800 hrs × 4/hr
    = 83,200
  • Calculations based on output

    The absorbed overhead may be ascertained using the data relating to output.

    Standard output for actual periods (days) and the overhead absorption rate per unit output are required for such a calculation.

    SO(AD) = BO ×
    AD
    BD
    = 2,000 units × 1.04
    = 2,080 units

    In the absence of information to the contrary we assume

    AbR/UO(F) = BR/UO(F)
    = 40

    Absorbed Fixed Overhead Cost ~ AbC(F)

    = SO(AD) × AbR/UO(F)
    = 2,080 units × 40/unit
    = 83,200

Building the working table with all the values needed and then using the formula based on values would be the simplest method to arrive at the value of the variance.

The method of absorption adopted and the method of calculation adopted would influence the calculation of the overhead absorbed only.

Fixed Overhead Volume Variance - Miscellaneous Aspects

  • Nature of Variance

    Based on the relations derived from the formulae for calculating FOHVOLV, we can identify the nature of Variance

    • AbC ___ BC

    The variance would be

    • zero when =
    • Positive when >
    • Negative when <
  • Interpretation of the Variance

    The following interpretations may be made

    No Variance

    The absorbed fixed overhead cost is the same as the budgeted cost

    Favourable/Favorable

    The absorbed fixed overhead cost is greater than the budgeted cost

    Adverse

    The absorbed fixed overhead cost is lesser than the budgeted cost
  • Who is answerable for the Variance?

    Fixed Overhead Volume Variance represents the gain or loss on account of putting the production facility to use to a greater/lesser extent. Those who are responsible for putting the production facility to use would be made answerable for the variance.
  • Reasons for variance can be further specified

    The fixed overhead volume variance would only let us know that the production facility has been put to use to a greater/lesser extent than planned/budgeted. It does not help us answer specific questions relating to the variance like, is it on account of the variation in the periods worked or the inputs used or efficiency.

    Taking the data from the above illustration, we can notice that variance in fixed overhead cost may be on account of

    • The actual overhead incurrence rate per unit time/output being different from the budgeted rate.

      Overhead Rate per unit - Actual 22 to 20 budgeted.

      Overhead Rate per unit time - Actual 2.02 to 2 budgeted.

    • The rate at which the output has been achieved is different from the budgeted rate.

      Time per unit output - 10.91 actual to 10 budgeted.

      Standard Actual Absorbed
      Budgeted for AO for AI for AP
      A B C
      a) Output (units)
      b) Periods (Days)
      c) Time (hrs)
      d) Overhead Cost
      ...
      g) Time/unit(hrs) (c) ÷ (a)
      2,000
      25
      20,000


      10






      2,050
      26
      22,360


      10.91
      The actual time per unit shown as 10.91 is an approximation of
      2,236
      205

    This specific identification can be obtained by breaking down the variance into its constituent parts.

Constituents of Fixed Overhead Volume Variance

Fixed overhead volume variance is a synthesis of four variances, Absorption, Capacity, Calendar and Efficiency.
FOHVOLV = AbC − BC
Adding and deduct SC(AO), SC(AI) and SC(AP) on the RHS
= AbC − BC + SC(AO) − SC(AO) + SC(AI) − SC(AI) + SC(AP) − SC(AP)
= AbC − SC(AO) + SC(AO) − SC(AI) + SC(AP) − BC + SC(AI) − SC(AP)
= [AbC − SC(AO)] + [SC(AO) − SC(AI)] + [SC(AP) − BC] + [SC(AI) − SC(AP)]
Taking time as input and days as periods
= [AbC − SC(AO)] + [SC(AO) − SC(AT)] + [SC(AD) − BC] + [SC(AT) − SC(AD)]
= Absorption Variance + Efficiency Variance + Calendar Variance + Capacity Variance
= FOHABSV + FOHEFFV + FOHCALV + FOHCAPV

Alternative

Where the overheads are being absorbed based on output and the budgeted rate is the absorption rate, then AbC = SC(AO).

In such a case the Absorption Variance does not exist and the Fixed Overhead Volume Variance may be divided into only three component parts, the capacity, calendar and efficiency variances.

FOHVOLV = AbC − BC
Adding and deduct SC(AI) and SC(AP) on the RHS
= AbC − BC + SC(AI) − SC(AI) + SC(AP) − SC(AP)
= AbC − SC(AI) + SC(AP) − BC + SC(AI) − SC(AP)
= [AbC − SC(AI)] + [SC(AP) − BC] + [SC(AI) − SC(AP)]
Taking time as input and days as periods
= [AbC − SC(AT)] + [SC(AD) − BC] + [SC(AT) − SC(AD)]
= Efficiency Variance + Calendar Variance + Capacity Variance
= FOHEFFV + FOHCALV + FOHCAPV

The only difference is in the terms that appear in the formula for efficiency variance and the absence of absorption variance. Absorbed cost (AbC) replaces standard cost of actual output [SC(AO)] in the formula for efficiency variance.

Formulae using Inter-relationships among Variances

  1. FOHVOLV = FOHCV − FOHEXPV
  2. FOHVOLV = FOHABSV + FOHCAPV + FOHCALV + FOHEFFV

Verification

The interrelationships between variances would also be useful in verifying whether our calculations are correct or not.
Basis of Absorption
Output Input
(Time)
Periods
(Days)
VOHABSV
+ VOHEFFV
+ VOHEXPV
0
− 3,720
− 4,480
+ 3,720
− 3,720
− 4,480
+ 600
− 3,720
− 4,480
a) VOHCV − 8,200 − 4,480 − 7,600
FOHCALV
+ FOHCAPV
+ FOHEFV






FOHVOLV
FOHEXPV
+ 2,000
+ 9,440
+ 3,200
b) FOHCV − 4,100 + 3,340 − 2,900
TOHCV (a) + (b) − 12,300 − 1,140 − 10,500

To enable understanding we have worked out the illustration under the three possible scenarios of overhead being absorbed on output, input and period basis.

Please be aware that only one of these methods would be in use.